[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898238":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898238,582,1,"单选题","(2014年)建设项目竣工财务决算应编制基本建设项目概况表，下列选项中应计入“基本建设项目概况表”非经营项目输出投资的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水土保持.城市绿化费用",false,{"key":16,"text":17,"correct":18},"B","产权不归属本单位的专用道路建设费",true,{"key":20,"text":21,"correct":14},"C","报废工程建设费",{"key":23,"text":24,"correct":14},"D","产权归本单位的地下管道建设费","本题考查的是竣工财务决算表。非经营性项目转出投资支出是指非经营项目为项目配套的专用设施投资，包括专用道路、专用通信设施、送表电站、地下管道等，其产权不属于本单位的投资支出，对于产权归属本单位的，应计入交付使用资产价值。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]