[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898234":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898234,582,1,"单选题","(2018年)某工业项目及其中Ⅰ车间的有关建设费用如下表所示，则Ⅰ车间应分摊的生产工艺设计费应为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","112.0",false,{"key":16,"text":17,"correct":14},"B","137.1",{"key":19,"text":20,"correct":21},"C","160.0",true,{"key":23,"text":24,"correct":14},"D","186.7","应分摊的工艺设计费=800\u002F2000×400=160 万元",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]