[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898225,582,1,"单选题","(2014年)在FIDIC合同条件中，工程是确认用于永久工程的材料和设备符合预支条件，在确定其实际费用后，其中支付证书中应增加改费用的（）作为工程材料和预备预支款。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","50%",false,{"key":16,"text":17,"correct":14},"B","60%",{"key":19,"text":20,"correct":14},"C","70%",{"key":22,"text":23,"correct":24},"D","80%",true,"本题考查的是国际工程合同价款的结算。工程师确认用于永久工程的材料和设备符合预支条件后，应当根据审查承包商提交的相关文件确定此类材料和设备的实际费用（包括运至现场的费用），期中支付证书中应增加的款额为该费用的80%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]