[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898223,582,1,"单选题","(2013年)根据《建设项目工程总承包合同示范文本GF-2011-0216》，下列说法正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预付款支付的时间和额度在通用条款中约定",false,{"key":16,"text":17,"correct":14},"B","预付款抵扣完后，承包人应及时向发包人退还预付款保函",{"key":19,"text":20,"correct":14},"C","发包人延误付款20天以上经催告仍不付款的，承包人即可停工",{"key":22,"text":23,"correct":24},"D","合同解除发包人有权要求承包人支付尚未扣完的预付款",true,"预付款在发包人签发工程接收证书或合同解除时，预付款尚未抵扣完时，发包人有权要求承包人支付尚未抵扣完的预付款。预付款的抵扣方式、抵扣比例和抵扣时间安排，由合同双方在专用条款中约定。预付款抵扣完后，发包人应及时向承包人退还预付款保函。P265：发包人延误付款15天以上，承包人有权向发包人发出要求付款的通知，发包人收到通知后仍不能付款的，承包人可以暂停部分工作，视为发包人导致的暂停，并按合同中关于发包人暂停的约定执行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]