[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898221":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898221,582,1,"单选题","(2011年)根据《建设工程工程量清单计价规范》(GB50500-2008)，关于索赔时限的规定的说法，错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A",",承包人应在确认引起索赔事件发生后28天内向发包人发出索赔通知",false,{"key":16,"text":17,"correct":14},"B","承包人应在确认引起索赔事件发生后42天内向发包人递交一份详细的索赔报告",{"key":19,"text":20,"correct":21},"C","对于具有连续影响的索赔事件，承包人应在该事件产生的影响结束后42天内，递交一份最终索赔报告",true,{"key":23,"text":24,"correct":14},"D","发包人在收到最终索赔报告的28天内未作答复即视为该索赔报告已经认可","承包人应在确认引起索赔事件发生后28天内向发包人发出索赔通知。承包人应在确认引起索赔事件发生后42天内向发包人递交一份详细的索赔报告。对于具有连续影响的索赔事件，承包人应在该事件产生的影响结束后28天内，递交一份最终索赔报告。发包人在收到最终索赔报告的28天内未作答复即视为该索赔报告已经认可。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]