[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898219":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898219,582,1,"单选题","(2015年)关于建设工程总承包合同价款的支付，下列说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预付款扣完后，由于工程尚未竣工，发包人可以不退还预付款保函",false,{"key":16,"text":17,"correct":18},"B","未约定预付款保函的，发包人在合同生效后规定时间内向承包人支付预付款金额",true,{"key":20,"text":21,"correct":14},"C","发包人延误付款，应自延误之日起按同期存款利率向承包人支付延期付款利息",{"key":23,"text":24,"correct":14},"D","发包人延误付款的，承包人有权直接暂停施工","该题主要考察的是：未约定预付款保函的。 A：预付款抵扣完后，发包人应及时向承包人退还预付款保函。 未约定预付款保函的，发包人在合同生效后10日内向承包人支付预付款金额。选项B正确。 选项C，发包人延误付款，应自延误之日起按同期贷款利率向承包人支付延期付款利息。 选项D，发包人延误付款15天以上，承包人有权向发包人发出要求付款的通知，发包人收到通知后仍不能付款的，承包人可暂停部分工作，视为发包人导致的暂停，并按合同中关于发包人暂停的约定执行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]