[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898205,582,1,"单选题","（2019年真题）发包人收到承包人提交的最终结清申请单，并在规定时间内予以核实后，向承包人签发（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程接收证书",false,{"key":16,"text":17,"correct":14},"B","竣工结算支付书",{"key":19,"text":20,"correct":14},"C","缺陷责任期终止证书",{"key":22,"text":23,"correct":24},"D","最终支付证书",true,"P263 发包人收到承包人提交的最终结清申请单后的规定时间内予以核实，向承包人签发最终支付证书。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]