[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898203":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898203,582,1,"单选题","(2018年)采用起扣点计算法扣回预付款的正确做法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从已完工程的累计合同额相当于工程预付款数额时起扣",false,{"key":16,"text":17,"correct":14},"B","从已完工程所用的主要材料及构件的价值相当于工程预付款数额时起扣",{"key":19,"text":20,"correct":21},"C","从未完工程所需的主要材料及构件的价值相当于工程预付款数额时起扣",true,{"key":23,"text":24,"correct":14},"D","从未完工程的剩余合同额相当于工程预付款数额时起扣","起扣点计算法，从未施工工程尚需的主要材料及构件的价值相当于工程预付款数额时起扣。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]