[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898201,582,1,"单选题","(2018年)工程量清单计价项目采用单价合同的，工程竣工结算编制中一般不允许调整的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程的清单数量",false,{"key":16,"text":17,"correct":14},"B","安全文明施工费的清单总额",{"key":19,"text":20,"correct":21},"C","已标价工程量清单综合单价",true,{"key":23,"text":24,"correct":14},"D","总承包服务费清单总额","采用单价合同的，在合同约定风险范围内的综合单价应固定不变，并应按合同约定进行计量，且应按实际完成的工程量进行计量",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]