[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898199,582,1,"单选题","(2018年)因不可抗力解除合同的，发包人不应向承包人支付的费用是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","临时工程拆除费",false,{"key":16,"text":17,"correct":18},"B","承包人未交付材料的货款",true,{"key":20,"text":21,"correct":14},"C","已实施的措施项目应付价款",{"key":23,"text":24,"correct":14},"D","承包人施工设备运离现场的费用","因不可抗力解除合同的，承包人未交付材料的货款不属于发包人不应向承包人支付的费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]