[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898195,582,1,"单选题","(2016年)由发包人提供的工程材料、工程设备的金额，应在合同价款的期中支付和结算中予以扣出。具体的扣出标准是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按签约单价和签约数量",true,{"key":16,"text":17,"correct":18},"B","按实际采购单价和实际数量",false,{"key":20,"text":21,"correct":18},"C","按签约单价和实际数量",{"key":23,"text":24,"correct":18},"D","按实际采购单价和签约数量","由发包人提供的材料、工程设备金额，应按照发包人签约提供的单价和数量从进度款支付中扣出，列入本周期应扣减的金额中。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]