[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898188,582,1,"单选题","(2014年)关于施工合同履行期间的期中支付，下列说法中正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","双方对工程计量结果的争议，不影响发包人对已完工工程的期中支付",false,{"key":16,"text":17,"correct":14},"B","对已签发支付证书中的计算错误。发包人不得再予修正",{"key":19,"text":20,"correct":21},"C","进度款制度申请中应包括累计已完成的合同价款",true,{"key":23,"text":24,"correct":14},"D","本周起实际支付的合同额为本期完成的合同价款合计","进度款支付申请：累计已完成的合同价款、累计已实际支付的合同价款、本周期合计完成的合同价款、本周期合计应扣减的金额、本周期实际应支付的合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]