[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898186":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898186,582,1,"单选题","(2013年)关于工程计量的方法，下列说法正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按照合同文件中规定的工程量予以计量",false,{"key":16,"text":17,"correct":18},"B","不符合合同文件要求的工程不予计量",true,{"key":20,"text":21,"correct":14},"C","单价合同工程量必须按现行定额规定的工程量计算规则计量",{"key":23,"text":24,"correct":14},"D","总价合同各项目的工程量是予以计量的最终工程量","单价合同工程量必须以承包人完成合同工程应予计量的按照现行国家计量规范规定的工程量计算规则计算得到的工程量确定。总价合同各项目的工程量是承包人用于结算的最终工程量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]