[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898184":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898184,582,1,"单选题","(2013年)在用起扣点计算法扣回预付款时，起扣点计算公式为T=P-M\u002FN，则式中N是指()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程预付款总额",false,{"key":16,"text":17,"correct":14},"B","工程合同总额",{"key":19,"text":20,"correct":21},"C","主要材料及构件所占比重",true,{"key":23,"text":24,"correct":14},"D","累计完成工程金额","P表示承包工程合同总额；M表示工程预付款总额；N表示主要材料及构件所占比重。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]