[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898179":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898179,582,1,"单选题","(2014年)某工程施工合同对于工程款付款时间约定不明、工程尚未交付、工程价款也未结算，现承包人起诉，发包人工程欠款利息应从（）之日计付。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程计划交付",false,{"key":16,"text":17,"correct":14},"B","提交竣工结算文件",{"key":19,"text":20,"correct":21},"C","当事人起诉",true,{"key":23,"text":24,"correct":14},"D","监理工程师暂定付款","本题考查的是工程欠款的利息支付。当事人对付款时间没有约定或者约定不明的，下列时间视为应付款时间： ①建设工程已实际交付的，交付之日；②建设工程没有交付的，为提交竣工结算文件之日；③建设工程未交付，工程价款也未结算的，为当事人起诉之日。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]