[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898178,582,1,"单选题","(2014年)关于最终结清，下列说法中正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","最终结清是在工程保修期满后对剩余质量保证金的最终结清",false,{"key":16,"text":17,"correct":14},"B","最终结清支付证书一经签发，承包人对合同内享有的索赔权利即自行终止",{"key":19,"text":20,"correct":14},"C","质量保证金不足以抵减发包人工程缺陷修复费用的，应按合同约定的争议解决方式处理",{"key":22,"text":23,"correct":24},"D","最终结清付款涉及政府投资的，应按国家集中支付相关规定和专用合同条款约定办理",true,"本题考查的是最终结算。最终结清付款涉及政府投资资金的，按照国库集中支付等国家相关规定和专用合同条款的约定办理。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]