[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898169,582,1,"单选题","（2019年真题）根据《标准施工招标文件》(2007年版)通用合同条款，下列引起承包人索赔的事件中,可以同时获得工期、费用和利润补偿的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工中发现文物、古迹",false,{"key":16,"text":17,"correct":18},"B","发包人延迟提供建筑材料",true,{"key":20,"text":21,"correct":14},"C","承包人提前竣工",{"key":23,"text":24,"correct":14},"D","因不可抗力造成工期延误","P245-253 根据《标准施工招标文件》，选项A能获得工期+费用补偿，选项C能获得费用补偿，选项D能获得工期补偿，只有选项B可同时获得工期、费用和利润补偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]