[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898167,582,1,"单选题","（2019年真题）下列发承包双方在约定调整合同价款的事项中属于工程变更的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单缺项",true,{"key":16,"text":17,"correct":18},"B","不可抗力",false,{"key":20,"text":21,"correct":18},"C","物价波动",{"key":23,"text":24,"correct":18},"D","提前竣工","P237-241 发承包双方按照合同约定调整合同价款的若干事项，可以分为五类：(1) 法规变化类，主要包括法律法规变化事件；(2) 工程变更类，主要包括工程变更、项目特征不符、工程量清单缺项、工程量偏差、计日工等事件；(3) 物价变化类，主要包括物价波动、暂估价事件；(4) 工程索赔类，主要包括不可抗力、提前竣工(赶工补偿)、误期赔偿、索赔等事件；(5) 其他类，主要包括现场签证以及发承包双方约定的其他调整事项，现场签证根据签证内容，有的可归于工程变更类，有的可归于索赔类，有的可能不涉及合同价款调整。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]