[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898166":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898166,582,1,"单选题","（2019年真题）某招标工程项目执行《建设工程工程量清单计价规范》(GB 50500—2013)，招标工程量清单中某分项工程的工程量为1500m3，施工中由于设计变更调增1900m3,该分项工程最高投标限价综合单价为40元\u002Fm3，投标报价为47元\u002Fm3，则该分项工程的结算价为（）元",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","87400",false,{"key":16,"text":17,"correct":14},"B","88900",{"key":19,"text":20,"correct":21},"C","89125",true,{"key":23,"text":24,"correct":14},"D","89300","P237-241 由于设计变更，工程量增加1900>1500*1.15=1725，超过部分1900-1725=175m3应采用新单价 投标报价47元\u002Fm3>40*1.15=46元\u002Fm3，因此超过部分175m3采用单价46元\u002Fm3 结算价为：1725*47+175*46=89125元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]