[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898165":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898165,582,1,"单选题","（2019年真题）某市政工程投标截止日期为2019年4月20日，确定中标人后，工程于2019年6月1日开工。施工合同约定，工程价款结算时人工、钢材、水泥、砂石料及施工机具使用费采用价格指数法调差，各项权重系数及价格指数见下表。2019年8月， 承包人当月完成清单子目价款2000万元，当月按已标价工程量清单价格确认的变更金额为200万元，则本工程2019年8月的价格调整金额为( )万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","57．80",false,{"key":16,"text":17,"correct":14},"B","63．58",{"key":19,"text":20,"correct":21},"C","75．40",true,{"key":23,"text":24,"correct":14},"D","82．94","P241-244 2000×【0.35+（0.15×105\u002F100+0.10×90\u002F84+0.20×107.8\u002F104.5+0.10×135\u002F115.6+0.1×110\u002F110）-1】=75.4万元",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]