[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898164":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898164,582,1,"单选题","（2019年真题）某施工现场主导施工机械一台，由承包人租得，施工合同约定，当发生索赔事件时，施工机械台班单价、租赁费分别按900元\u002F台班、400元\u002F台班计；人工工资、窝工费分别按100元\u002F工日、50元\u002F工日计，以人工费与机械费之和为基数的综合费率为30%，在施工过程中，发生如下事件：①出现异常恶劣天气导致工程停工2天，人员窝工20个工日；②因恶劣天气导致工程修复用工10个工日，主导小机械1个台班，为此承包人可向发包人索赔的费用为（）元",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1820",false,{"key":16,"text":17,"correct":18},"B","2470",true,{"key":20,"text":21,"correct":14},"C","2820",{"key":23,"text":24,"correct":14},"D","3470","P245-253 (10*100+1*900)*(1+30%)=2470元",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]