[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898159,582,1,"单选题","(2018年)发包人在招标工程量清单中给定某工程设备暂估价，下列关于该工程设备价款调整的说法正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","依法可不招标的项目，应由发包人组织采购，以采购价格取代暂估价",false,{"key":16,"text":17,"correct":18},"B","依法可不招标的项目，应由承包人按合同约定采购，以发包人确认后的价格取代暂估价",true,{"key":20,"text":21,"correct":14},"C","依法必须招标的项目，应由发包人招标选择供应商，以中标价格取代暂估价",{"key":23,"text":24,"correct":14},"D","依法必须招标的项目，应由承包人招标选择供应商，以中标价格取代暂估价","依法可不招标的项目，应由承包人按合同约定采购，以发包人确认后的价格取代暂估价，A 错误；发包人在招标工程量清单中给定暂估价的材料和工程设备属于依法必须招标的，由发承包双方以招标的方式选择供应商，CD 错误。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]