[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898157,582,1,"单选题","(2018年)根据《标准施工招标文件》（2007 年版）通用合同条款，下列引起承包人索赔的事件中，只能获得费用补偿的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人提前向承包人提供材料、工程设备",true,{"key":16,"text":17,"correct":18},"B","因发包人提供的材料、工程设备造成工程不合格",false,{"key":20,"text":21,"correct":18},"C","发包人在工程竣工前提前占用工程",{"key":23,"text":24,"correct":18},"D","异常器劣的气候条件，导致工期延误","发包人提前向承包人提供材料、工程设备只能得到费用补偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]