[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898155,582,1,"单选题","（2017年考题）某分项工程招标工程量清单数量为 4000㎡，施工中由于设计变更调减为 3000㎡，该项目招标控制价综合单价为 600元\u002F㎡，投标报价为 450元\u002F㎡。合同约定实际工程量与招标工程量偏差超过±15%时，综合单价以招标控制价为基础调整。若承包人报价浮动率为 10%，该分项工程费结算价为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","137.70",true,{"key":16,"text":17,"correct":18},"B","155.25",false,{"key":20,"text":21,"correct":18},"C","186.30",{"key":23,"text":24,"correct":18},"D","207.00","工程量减少超过 15%；报价偏差超过 15%；调整后价格=600×（1-10%）×（1-15%）=459元\u002F㎡＞450元\u002F㎡，该项目结算价=459×3000=137.7万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]