[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898154,582,1,"单选题","(2016年)采用网络图分析法处理可原谅延期，下列说法中正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","只有在关键线路上的工作延误，才能索赔工期",false,{"key":16,"text":17,"correct":14},"B","非关键线路上的工作延误，不应索赔工期",{"key":19,"text":20,"correct":21},"C","如延误的工作为关键工作，则延误的时间为工期索赔值",true,{"key":23,"text":24,"correct":14},"D","该方法不适用于多种干扰事件共同作用所引起的工期索赔","3)网络图分析法。网络图分析法是利用进度计划的网络图，分析其关键线路。如果延误的工作为关键工作，则延误的时间为索赔的工期；如果延误的工作为非关键工作，当该工作由于延误超过时差限制而成为关键工作时，可以索赔延误时间与时差的差值；若该工作延误后仍为非关键工作，则不存在工期索赔问题。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]