[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898153,582,1,"单选题","(2016年)某工程施工过程中发生如下事件：①因异常恶劣气候条件导致工程停工2天，人员窝工20个工日；②遇到不利地质条件导致工程停工1天，人员窝工10个工日，处理不利地质条件用工15个工日。若人工工资为200元\u002F工日，窝工补贴为100元\u002F工日，不考虑其他因素。根据《标准施工招标文件》（2007年版）通用合同条款，施工企业可向业主索赔的工期和费用分别是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3天，6000元",false,{"key":16,"text":17,"correct":14},"B","1天，3000元",{"key":19,"text":20,"correct":21},"C","3天，4000元",true,{"key":23,"text":24,"correct":14},"D","1天，4000元","《标准施工招标文件》中承包人的索赔事件及可补偿内容施工中遇到不利物质条件，可索赔工期和费用；异常恶劣的气候条件导致工期延误，可索赔工期。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]