[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898152,582,1,"单选题","(2016年)根据《招标施工招标文件》（2007年版）通用合同条款，承包人最有可能同时获得工期、费用和利润补偿的索赔事件是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基准日后法律的变化",false,{"key":16,"text":17,"correct":14},"B","发包人更换其提供的不合格材料",{"key":19,"text":20,"correct":14},"C","发包人提前向承包人提供工程设备",{"key":22,"text":23,"correct":24},"D","发包人在工程竣工前占用工程",true,"",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]