[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898150,582,1,"单选题","(2015年)根据《标准施工招标文件》（2007年版）的合同通用条件，承包人通常只能获得费用补偿，但不能得到利润补偿和工期顺延的事件是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工中遇到不利物质条件",false,{"key":16,"text":17,"correct":14},"B","因发包人的原因导致工程试运行失败",{"key":19,"text":20,"correct":14},"C","发包人更换其提供的不合格材料",{"key":22,"text":23,"correct":24},"D","基准日后法律的变化",true,"选项A可以索赔工期和费用，选项B可以索赔费用和利润；选项C可以索赔工期费用；选项D只可以索赔费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]