[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898141":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898141,582,1,"单选题","(2013年)根据规定，因工程量偏差引起的可以调整措施项目费的前提是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同工程量偏差超过15%",false,{"key":16,"text":17,"correct":18},"B","合同工程量偏差超过15%，且引起措施项目相应变化",true,{"key":20,"text":21,"correct":14},"C","措施项目工程量超过10%",{"key":23,"text":24,"correct":14},"D","措施项目工程量超过10%，且引起施工方案发生变化","措施项目费的调整，当工程量偏差超过15%，且该变化引起措施项目相应发生变化，如该措施项目是按系数或单一总价方式计价的，对措施项目费的调整原则为：工程量增加的，措施项目费调增；工程量减少的，措施项目费调减。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]