[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898140":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898140,582,1,"单选题","(2013年)关于共同延误的处理原则，下列说法中正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","初始延误者负主要责任，并发延误者负次要责任",false,{"key":16,"text":17,"correct":14},"B","初始延误者属发包人原因的，承包人可得工期补偿，但无经济补偿",{"key":19,"text":20,"correct":21},"C","初始延误者属客观原因的，承包人可得工期补偿，但很难得到费用补偿",true,{"key":23,"text":24,"correct":14},"D","初始延误者属发包人原因的，承包人可获得工期和费用补偿，但无利润补偿","共同延误的处理原则：①确定初始延误者，它应对工程拖期负责；②如果初始延误者是发包人原因，则承包人既可得到工期延长，又可得到经济补偿；③如果初始延误者是客观原因，则承包人可以得到工期延长，但很难得到费用补偿；④如果初始延误看是承包人原因，则承包人既不能得到工期补偿，也不能得到费用补偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]