[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898139,582,1,"单选题","(2013年)由于发包人原因导致工期延误的，对于计划进度日期后续施工的工程，在使用价格调整公式时，现行价格指数应采用()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划进度日期的价格指数",false,{"key":16,"text":17,"correct":14},"B","实际进度日期的价格指数",{"key":19,"text":20,"correct":14},"C","A和B中较低者",{"key":22,"text":23,"correct":24},"D","A和B中较高者",true,"于发包人原因导致工期延误的，则对于计划进度日期(或竣工日期）后续施工的工程，在使用价格调整公式时，应采用计划进度日期（或竣工日期）与实际进度日期（或竣工日期）的两个价格指数中较高者作为现行价格指数。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]