[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898138,582,1,"单选题","(2013年)对于实行招标的建设工程，因法律法规政策变化引起合同价款调整的，调价基准日期一般为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工合同签订前的第28天",false,{"key":16,"text":17,"correct":18},"B","提交投标文件的截止时间前的第28天",true,{"key":20,"text":21,"correct":14},"C","施工合同签订前的第56天",{"key":23,"text":24,"correct":14},"D","提交投标文件截止时间前的第56天","对于实行招标的建设工程，一般以施工招标文件中规定的提交投标文件的截止时间前的第28天作为基准日；对于不实行招标的建设工程，一般以建设工程施工合同签订前的第28天作为基准日。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]