[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898134,582,1,"单选题","(2015年)某建筑工程钢筋综合用量1000t。施工合同中约定，结算时对钢筋综合价格涨幅5%以上部分依据造价处发布的基准价调整价格差额。承包人投标报价2400元\u002Ft，投标期、施工期间造价管理机构发布的钢筋综合基准价格为2500元\u002Ft、2800元\u002Ft，则需调增钢筋材料费用为( )万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","17.5",true,{"key":16,"text":17,"correct":18},"B","28.0",false,{"key":20,"text":21,"correct":18},"C","30.0",{"key":23,"text":24,"correct":18},"D","40.0","投标期间造价管理机构发布价为2500，施工期间发布为2800，上涨300，上涨率：300\u002F2500=12%，超5%，调价部分为（12%-5%=7%），7%×2500=175元，综合用量为1000T，总调增为1000×175=17.5万 考点是：投标报价低于基准单价的，涨幅以基准单价为准，跌幅以投标报价为准。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]