[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898133,582,1,"单选题","(2014年)施工合同履行期间，关于计日工费用的处理，下列说法中正确的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已招标价工程量清单中无某项计日工单价时候，应按工程变更有关规定商定计日工单价",true,{"key":16,"text":17,"correct":18},"B","承包人通知发包人以计日方式实施的零量工作，双方应按计日工方式予以结算",false,{"key":20,"text":21,"correct":18},"C","现场签证的计日工数量与招标工程量清单中所列不同时，应按工程变更有关规定进行价款调整",{"key":23,"text":24,"correct":18},"D","施工各期间发生的计日工费用应在竣工结算时一并支付","本题考查的是计日工的费用的确认和支付。已标价工程量清单中没有该类计日工单价的，由发承包双方按照工程变更的有关规定商定计日单价计算。B应该是发包人对承包人，不是承包人对发包人。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]