[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898122,582,1,"单选题","(2016年)国际工程投标报价中，若将分包费列入直接费，则对分包商的管理费通常应列入()中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直接费",false,{"key":16,"text":17,"correct":14},"B","分包费",{"key":19,"text":20,"correct":21},"C","间接费",true,{"key":23,"text":24,"correct":14},"D","暂定金额","(2)分包费。在国际工程标价中，对分包费的处理有两种方法：一种方法是将分包费列人直接费中，即考虑间接费时包含了对分包的管理费；另一种方法是将分包费与直接费、间接费平行并列，在估算分包费时适当加入对分包商的管理费即可。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]