[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898119,582,1,"单选题","(2015年)根据《标准设计施工总承包招标文件》，除投标人须知前附表另有规定外，工程总承包招标的投标有效期为()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","60",false,{"key":16,"text":17,"correct":14},"B","90",{"key":19,"text":20,"correct":21},"C","120",true,{"key":23,"text":24,"correct":14},"D","180","该题主要考察的是：总承包投标文件的编制时应遵循的规定 “由于实施工程总承包的项目通常比较复杂，因此除投标人须知前附表另有规定外，投标有效期均为120天。”",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]