[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898113,582,1,"单选题","(2015年)按照世界银行有关规定进行的国际竞争性招标，在中标人确定后还应进行合同谈判。下列主题中属于合同谈判内容的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同价格的优惠",false,{"key":16,"text":17,"correct":14},"B","合同双方的权利和义务",{"key":19,"text":20,"correct":21},"C","合同标的物数量增减引起的价格变化",true,{"key":23,"text":24,"correct":14},"D","投标人承担技术规格书中设有规定的额外任务","该题主要考察的是：国际工程招标投标及合同价款的约定 “(1)原招标文件中规定采购的设备、货物或工程的数量可能有所增减，合同总价也随之可按单价计算而有增减； (2)投标人的投标，对原招标文件中提出的各种标准及要求，总会有一些非重大性的差异。如技术规格上某些重大的差别，交货或完工时间提前或推迟，工程预付款的多少及支付条件，损失赔偿的具体规定，价格调整条款及所依据的指数的确定等，都应在谈判中进一步明确。”",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]