[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898102":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898102,582,1,"单选题","(2016年)某招标项目采用经评审的最低投标价法评标，招标文件规定对同时投多个标段的评标修正率为5%，投标人甲同时投标1#、2#标段，报价分别为5000万元、4000万元。若甲在1#标段中标，则其在2#标段的评标为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3750",false,{"key":16,"text":17,"correct":18},"B","3800",true,{"key":20,"text":21,"correct":14},"C","4200",{"key":23,"text":24,"correct":14},"D","4250","对同时投多个标段的评标修正，一般的做法是，如果投标人的某一个标段已被确定为中标，则在其他标段的评标中按照招标文件规定的百分比通常为4%)乘以报价额后，在评标价中扣减此值。投标人甲在1#标段中标后，其在2#标段的评标可享受5%的评标优惠，具体做法应是将其2#标段的投标报价乘以4%，在评标价中扣减该值。因此投标人甲2#标段的评标价=4000×(1-5%)=3800(万元）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]