[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898099":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898099,582,1,"单选题","(2014年)招标工程未进行资格预审，评审委员会按规定对投标人安全生产许可证的有效性进行的评审属于（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","形式评审",false,{"key":16,"text":17,"correct":18},"B","资格评审",true,{"key":20,"text":21,"correct":14},"C","响应性评审",{"key":23,"text":24,"correct":14},"D","商务评审","2)资格评审标准。如果是未进行资格预审的，应具备有效的营业执照，具备有效的安全生产许可证，并且资质等级、财务状况、类似项目业绩、信誉、项目经理、其他要求、联合体投标人等，均符合规定。如果是已进行资格预审的，仍按资格审查办法中详细审查标准来进行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]