[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898089":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898089,582,1,"单选题","（2019年真题）在投标报价确定分部分项工程综合单价时，应根据所选的计算基础计算工程内容的工程量，该数量应为（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实物工程量",false,{"key":16,"text":17,"correct":14},"B","施工工程量",{"key":19,"text":20,"correct":21},"C","定额工程量",true,{"key":23,"text":24,"correct":14},"D","复核的清单工程量","P200-209 计算工程内容的工程数量与清单单位的含量时，每一项工程内容都应根据所选定额的工程量计算规则计算其工程数量，当定额的工程量计算规则与清单的工程量计算规则相一致时，可直接以工程量清单中的工程量作为工程内容的工程数量。当采用清单单位含量计算人工费、材料费、施工机具使用费时，还需要计算每一计量单位的清单项目所分摊的工程内容的工程数量，即清单单位含量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]