[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898088":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},898088,582,1,"单选题","(2018年)关于工程施工投标报价过程中的工程量的复核，下列说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","复核的准确程度不会影响施工方法的选用",false,{"key":16,"text":17,"correct":14},"B","复核的目的在于修改工程量清单中的工程量",{"key":19,"text":20,"correct":21},"C","复核有助于防止由于物资少购带来的停工待料",true,{"key":23,"text":24,"correct":14},"D","复核中发现的遗漏和错误须向招标人提出","复核的准确程度会影响施工方法的选用，A 错误；复核的目的不是在于修改工程量清单中的工程量，B 错误；针对工程量清单中工程量的遗漏或错误，是否向招标人提出修改意见取决于投标策略，D 错误。 考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]