[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898085":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898085,582,1,"单选题","(2018年)施工投标报价工作包括：①工程现场调查；②组建投标报价班子；③确定基础标价；④制订项目管理规划；⑤复核清单工程量。下列工作排序正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①④②③⑤",false,{"key":16,"text":17,"correct":14},"B","②③④①⑤",{"key":19,"text":20,"correct":14},"C","①②③④⑤",{"key":22,"text":23,"correct":24},"D","②①⑤④③",true,"施工投标报价工作分为前期工作、调查询价和报价编制。组建投标报价班子和工程现场调查属于投标报价编制的前期工作，复核工程量和制订项目管理规划属于调查询价，确定基础报价属于报价编制。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]