[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898080":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898080,582,1,"单选题","(2016年)投标人在投标报价时，应优先被采用为综合单价编制依据的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业定额",true,{"key":16,"text":17,"correct":18},"B","地区定额",false,{"key":20,"text":21,"correct":18},"C","行业定额",{"key":23,"text":24,"correct":18},"D","国家定额","(2)综合单价确定的步骤和方法 1)确定计算基础 计算时应采用企业定额，在没有企业定额或企业定额缺项时，可参照本企业实际水平相近的国家、地区、行业定额，并通过调整来确定清单项目的人、材、机单位用量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]