[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898077":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898077,582,1,"单选题","(2015年)关于投标报价时综合单价的确定，下列做法中正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以项目特征描述为依据确定综合单价",true,{"key":16,"text":17,"correct":18},"B","招标工程量清单特征描述与设计图纸不符时，应以设计图纸为准",false,{"key":20,"text":21,"correct":18},"C","应考虑招标文件规定范围（幅度）外的风险费用",{"key":23,"text":24,"correct":18},"D","消耗量指标的计算应以地区或行业定额为依据","选项A正确：项目特征是确定综合单价的重要依据之一，投标人投标报价时应依据招标文件中清单项目的特征描述确定综合单价。选项B错误：在招标投标过程中，当出现招标工程量清单特征描与设计图纸不符时，投标人应以招标工程量清单的项目特征描述为准，确定投标报价的综合单价。 选项C错误：招标文件中要求投标人承担的风险费用，投标人应考虑进入综合单价。 选项D错误，消耗量指标应根据本企业的企业实际消耗量水平计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]