[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898076,582,1,"单选题","(2014年)关于工程量清单方式招标工程合同价格风险及风险分担，下列说法中正确的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当出现的风险内容及幅度在招标文件规定的范围内时，综合单价不变",true,{"key":16,"text":17,"correct":18},"B","市场价格波动导致施工机具使用费发生变化时，承包人只承担5%以内的价格风险",false,{"key":20,"text":21,"correct":18},"C","人工费变化发生的风险全部由发包人承担",{"key":23,"text":24,"correct":18},"D","承包人管理费的风险一般由发承包双方共同承担","本题考查的是工程清单的风险承担原则。B选项，施工单位承担10%以内的施工机具使用费的风险；C选项应是法律法规等导致的人工费的变化，承包人不再承担风险；D选项，承包人的管理费用由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]