[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898072,582,1,"单选题","(2010年)工程量清单计价模式下，确定分部分项工程单价的工作包括：①分析各清单项目的工程内容，②确定计算基础，③计算人工、材料、机械费用，④计算工程内容的工程量与清单单位含量，⑤计算综合单价。对上述工作先后顺序的排列，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②④⑤③",false,{"key":16,"text":17,"correct":18},"B","②①④③⑤",true,{"key":20,"text":21,"correct":14},"C","①②④⑧⑤",{"key":23,"text":24,"correct":14},"D","②①④⑤③","分部分项工程单价确定的步骤为：①确定计算基础；②分析每一清单项目的工程内容；③计算工程内容的工程数量与清单单位的含量；④分部分项工程人工、材料、机械费用的计算；⑤计算综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]