[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898056,582,1,"单选题","(2018年)关于工程量清单“量价分离”和“风险分担”的编制原则，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标人对已标价工程量清单中各分部分项工程量的准确性和完整性负责",true,{"key":16,"text":17,"correct":18},"B","招标人对已标价工程量清单中措施项目工程量的准确性和完整性负责",false,{"key":20,"text":21,"correct":18},"C","投标人对已标价工程量清单中各分部分项工程量的准确性和完整性负责",{"key":23,"text":24,"correct":18},"D","投标人对已标价工程量清单中措施项目工程量的准确性和完整性负责","招标人对工程量清单中各分部分项工程或适合以分部分项工程量清单设置的措施项目的工程量的准确性和完整性负责；投标人应结合企业自身实际、参考市场有关价格信息完成清单项目工程的组合报价，并对其承担风险。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]