[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},898054,582,1,"单选题","(2018年)根据《建设工程工程量清单计价规范》(GB50500-2013)中对招标控制价的相关规定，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标控制价公布后根据需要可以上浮或下调",false,{"key":16,"text":17,"correct":14},"B","招标人可以只公布招标控制价总价，也可以只公布单价",{"key":19,"text":20,"correct":14},"C","招标控制价可以在招标文件中公布，也可以在开标时公布",{"key":22,"text":23,"correct":24},"D","高于招标控制价的投标报价应被拒绝",true,"招标控制价应在招标文件中公布，对所编制的招标控制价不得进行上浮或下调，AC 错；招标人应当在招标时公布招标控制价的总价，以及各单位工程的分部分项工程费、措施项目费、其他项目费、规费和税金，B错",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]