[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898051":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},898051,582,1,"单选题","(2016年)根据《标准施工招标文件》（2007年版），关于“分包和偏差问题处理”的内容应包括于（ ）之中。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标公告",false,{"key":16,"text":17,"correct":18},"B","投标人须知",true,{"key":20,"text":21,"correct":14},"C","评标办法",{"key":23,"text":24,"correct":14},"D","合同条款与格式","(2)投标人须知。投标人须知包括10个内容：1)总则。主要包括项目概况、资金来源和落实情况、招标范围、计划工期和质量要求的描述，对投标人资格要求的规定，对费用承担、保密、语言文字、计量单位等内容的约定，对踏勘现场、投标预备会的要求，以及对分包和偏离问题的处理。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]