[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-898049":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},898049,582,1,"单选题","(2015年)关于招标工程量清单中分部分项工程量清单的编制，下列说法中错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标人只负责项目编码、项目名称、计量单位和工程量四项内容的填写",true,{"key":16,"text":17,"correct":18},"B","同一招标工程的项目编码不得有重复",false,{"key":20,"text":21,"correct":18},"C","清单所列项目应是在单位工程施工过程中以其本身构成该工程实体的分项工程",{"key":23,"text":24,"correct":18},"D","当清单计价规范附录中有两个计量单位时，应结合实际情况选择其中一个","该题主要考察的是：分部分项工程量清单的编制 “分部分项工程项目清单所反映的是拟建工程分部分项工程项目名称和相应数量的明细清单，招标人负责包括项目编码、项目名称、项目特征、计量单位和工程量在内的5项内容。”",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]